Renergia
EN RO
← All case studies
Industry 01 June – 07 July 2026

Increasing solar self-consumption

Renergia analysed the hourly electricity consumption and photovoltaic production of an industrial bakery and milling site to find how more locally generated solar energy could be used and how purchased electricity could be reduced.

10 kW → 70 kW Photovoltaic capacity after the recommended 60 kW extension
183.8 kWh / day Average impact of photovoltaic expansion and load shifting
€49.60 / day Average avoided electricity cost on monitored milling days
73.8% self-consumption Average across monitored milling operating days
33.8% less grid power Estimated reduction from the combined measures

Context

The industrial site covers several buildings and operational areas. It already had a 10 kW photovoltaic system, but the available solar production was not aligned with the site’s largest electricity demand.

Renergia analysed hourly consumption and solar production, including an additional monitored week between 02 and 07 July 2026. Grid purchases were estimated because import and export were not measured directly.

10 kW

Existing photovoltaic system

Bakery & milling

Pastry, confectionery, flour milling

02–07 Jul 2026

Additional monitored week

What Renergia found

Renergia identified two opportunities. The existing 10 kW system was too small to cover a significant share of the site’s daytime consumption, and the largest milling consumption peak occurred in the morning, before photovoltaic production reached its highest level.

Moving part of the milling activity into the afternoon would allow the site to use more locally generated energy and purchase less electricity from the grid.

What we did

Renergia recommended a combination of new capacity and an operational change to align demand with solar production.

01

Photovoltaic expansion

Recommended increasing installed photovoltaic capacity by 60 kW, from 10 kW to 70 kW.

02

Operational load shifting

Recommended moving part of the milling process into the period with the highest photovoltaic production, shifting the monitored peak from 110.2 kWh/h at 09:00 to 87.7 kWh/h at 13:00.

Before vs. after

Aligning the milling schedule with solar production reduced both the milling peak and the electricity purchased from the grid.

Milling consumption peak

−20.4%
Before
110.2 kWh/h
After
87.7 kWh/h

Purchased electricity (reference → combined measures)

−33.8%
Before
544 kWh
After
361 kWh

What we achieved

Adding capacity helped, but the combined measures cut purchased electricity by a third on monitored milling days.

Reference scenario — purchased electricity 544 kWh
Photovoltaic expansion only 470 kWh · −13.7%

74.6 kWh / €20.10 saved per operating day.

Expansion + load shifting 361 kWh · −33.8%

183.8 kWh / €49.60 saved per operating day — not a monthly or annual figure.

Projected over 30 operating days (PV only) 2,238 kWh · €604
Projected over 30 operating days (combined) 5,514 kWh · €1,489

Why it matters

Adding more photovoltaic capacity produced clear savings, but the stronger result came from combining new technology with a change in the operating schedule.

By aligning the milling process with the solar production window, the site could use more locally generated electricity, reduce grid purchases, and improve the return on its photovoltaic investment.

Want results like these in your buildings?